10 U.S.C. § 225
Title 10
Chapter 9
Current through PL 116-220
~4 min read
Last updated: March 30, 2026
View on OLRC →
Sections in this chapter
§ 225. Acquisition accountability reports on the ballistic missile defense system
- (a)
- (1) In accordance with paragraph (2), the Director of the Missile Defense Agency shall establish and maintain an acquisition baseline for—
- (A) each program element of the ballistic missile defense system, as specified in section 223 of this title ; and
- (B) each designated major subprogram of such program elements.
- (2) The Director shall establish an acquisition baseline required by paragraph (1) before the date on which the program element or major subprogram enters—
- (A) engineering and manufacturing development (or its equivalent); and
- (B) production and deployment.
- (3) Except as provided by subsection (d), the Director may not adjust or revise an acquisition baseline established under this section.
- (1) In accordance with paragraph (2), the Director of the Missile Defense Agency shall establish and maintain an acquisition baseline for—
- (b) Each acquisition baseline required by subsection (a) for a program element or major subprogram shall include the following:
- (1) A comprehensive schedule, including—
- (A) research and development milestones;
- (B) acquisition milestones, including design reviews and key decision points;
- (C) key test events, including ground and flight tests and ballistic missile defense system tests;
- (D) delivery and fielding schedules;
- (E) quantities of assets planned for acquisition and delivery in total and by fiscal year; and
- (F) planned contract award dates.
- (2) A detailed technical description of—
- (A) the capability to be developed, including hardware and software;
- (B) system requirements, including performance requirements;
- (C) how the proposed capability satisfies a capability identified by the commanders of the combatant commands on a prioritized capabilities list;
- (D) key knowledge points that must be achieved to permit continuation of the program and to inform production and deployment decisions; and
- (E) how the Director plans to improve the capability over time.
- (3) A cost estimate, including—
- (A) a life-cycle cost estimate that separately identifies the costs regarding research and development, procurement, military construction, operations and sustainment, and disposal;
- (B) program acquisition unit costs for the program element;
- (C) average procurement unit costs and program acquisition costs for the program element; and
- (D) an identification of when the document regarding the program joint cost analysis requirements description is scheduled to be approved.
- (4) A test baseline summarizing the comprehensive test program for the program element or major subprogram outlined in the integrated master test plan.
- (1) A comprehensive schedule, including—
- (c)
- (1) Not later than February 15 of each year, the Director shall submit to the congressional defense committees a report on the acquisition baselines required by subsection (a).
- (2)
- (A) The first report under paragraph (1) shall set forth each acquisition baseline required by subsection (a) for a program element or major subprogram.
- (B) Each subsequent report under paragraph (1) shall include—
- (i) any new acquisition baselines required by subsection (a) for a program element or major subprogram; and
- (ii) with respect to an acquisition baseline that was previously included in a report under paragraph (1), an identification of any changes or variances made to the elements described in subsection (b) for such acquisition baseline, as compared to—
- (I) the initial acquisition baseline for such program element or major subprogram; and
- (II) the acquisition baseline for such program element or major subprogram that was submitted in the report during the previous year.
- (3) Each report under this subsection shall be submitted in unclassified form, but may include a classified annex.
- (d) The Director may adjust or revise an acquisition baseline established under this section if the Director submits to the congressional defense committees notification of—
- (1) a justification for such adjustment or revision;
- (2) the specific adjustments or revisions made to the acquisition baseline, including to the elements described in subsection (b); and
- (3) the effective date of the adjusted or revised acquisition baseline.
- (e) The Director shall ensure that each life-cycle cost estimate included in an acquisition baseline pursuant to subsection (b)(3)(A) includes—
- (1) all of the operations and sustainment costs for which the Director is responsible; and
- (2) a description of the operations and sustainment functions and costs for which a military department is responsible.
Change History
No amendments tracked yet for this section.
Change history will appear here automatically when the pipeline detects modifications between US Code release points.