§ 5514. Acquisition accountability on the missile defense system

  • (a)
    • (1) In accordance with paragraph (2), the Director of the Missile Defense Agency shall establish and maintain an acquisition baseline for—
      • (A) each program element of the missile defense system, as specified in section 223 1 1 See References in Text note below. of this title; and
      • (B) each designated major subprogram of such program elements.
    • (2) The Director shall establish an acquisition baseline required by paragraph (1) before the date on which the program element or major subprogram enters—
      • (A) engineering and manufacturing development (or its equivalent); and
      • (B) production and deployment.
    • (3) Except as provided by subsection (c), the Director may not adjust or revise an acquisition baseline established under this section.
  • (b) Each acquisition baseline required by subsection (a) for a program element or major subprogram shall include the following:
    • (1) A comprehensive schedule, including—
      • (A) research and development milestones;
      • (B) acquisition milestones, including design reviews and key decision points;
      • (C) key test events, including ground, flight, and cybersecurity tests and ballistic missile defense system tests;
      • (D) delivery and fielding schedules;
      • (E) quantities of assets planned for acquisition and delivery in total and by fiscal year; and
      • (F) planned contract award dates.
    • (2) A detailed technical description of—
      • (A) the capability to be developed, including hardware and software;
      • (B) system requirements, including performance requirements;
      • (C) how the proposed capability satisfies a capability requirement or performance attribute identified through—
        • (i) the missile defense warfighter involvement process, as governed by United States Strategic Command Instruction 538–03, or such successor document; or
        • (ii) processes and products reviewed by the Joint Chiefs of Staff or Joint Requirements Oversight Council;
      • (D) key knowledge points that must be achieved to permit continuation of the program and to inform production and deployment decisions; and
      • (E) how the Director plans to improve the capability over time.
    • (3) A cost estimate, including—
      • (A) a life-cycle cost estimate that separately identifies the costs regarding research and development, procurement, military construction, operations and sustainment, and disposal;
      • (B) program acquisition unit costs for the program element;
      • (C) average procurement unit costs and program acquisition costs for the program element;
      • (D) an identification of when the document regarding the program joint cost analysis requirements description is scheduled to be approved; and
      • (E) an explanation for why a program joint cost analysis requirements description has not been prepared and approved, and, if a program joint cost analysis requirements description is not applicable, the rationale for such inapplicability.
    • (4) A test baseline summarizing the comprehensive test program for the program element or major subprogram outlined in the integrated master test plan.
  • (c) The Director may adjust or revise an acquisition baseline established under this section if the Director submits to the congressional defense committees notification of—
    • (1) a justification for such adjustment or revision;
    • (2) the specific adjustments or revisions made to the acquisition baseline, including to the elements described in subsection (b); and
    • (3) the effective date of the adjusted or revised acquisition baseline.
  • (d) The Director shall ensure that each life-cycle cost estimate included in an acquisition baseline pursuant to subsection (b)(3)(A) includes—
    • (1) all of the operations and sustainment costs for which the Director is responsible;
    • (2) a description of the operations and sustainment functions and costs for which a military department is responsible;
    • (3) the amount of operations and sustainment costs (dollar value and base year) for which the military department or other element of the Department of Defense is responsible; and
    • (4)
      • (A) a citation to the source (such as a joint cost estimate or one or more military department estimates) that captures the operations and sustainment costs for which a military department or other element of the Department of Defense is responsible;
      • (B) the date the source was prepared; and
      • (C) if and when the source was independently verified by the Office for Cost Assessment and Program Evaluation.