§ 4371. Cost growth definitions; applicability of reporting requirements; constant base year dollars

  • (a) In this chapter:
    • (1) Except as provided in section 4203(d) of this title , the terms “program acquisition unit cost”, “procurement unit cost”, and “major contract” have the same meanings as provided in section 4351(a) of this title .
    • (2) The term “significant cost growth threshold” means the following:
      • (A) In the case of a major defense acquisition program or designated major defense subprogram, a percentage increase in the program acquisition unit cost for the program or subprogram of—
        • (i) at least 15 percent over the program acquisition unit cost for the program or subprogram as shown in the current Baseline Estimate for the program or subprogram; or
        • (ii) at least 30 percent over the program acquisition unit cost for the program or subprogram as shown in the original Baseline Estimate for the program or subprogram.
      • (B) In the case of a major defense acquisition program or designated major defense subprogram that is a procurement program, a percentage increase in the procurement unit cost for the program or subprogram of—
        • (i) at least 15 percent over the procurement unit cost for the program or subprogram as shown in the current Baseline Estimate for the program or subprogram; or
        • (ii) at least 30 percent over the procurement unit cost for the program or subprogram as shown in the original Baseline Estimate for the program or subprogram.
    • (3) The term “critical cost growth threshold” means the following:
      • (A) In the case of a major defense acquisition program or designated major defense subprogram, a percentage increase in the program acquisition unit cost for the program or subprogram of—
        • (i) at least 25 percent over the program acquisition unit cost for the program or subprogram as shown in the current Baseline Estimate for the program or subprogram; or
        • (ii) at least 50 percent over the program acquisition unit cost for the program or subprogram as shown in the original Baseline Estimate for the program or subprogram.
      • (B) In the case of a major defense acquisition program or designated major defense subprogram that is a procurement program, a percentage increase in the procurement unit cost for the program or subprogram of—
        • (i) at least 25 percent over the procurement unit cost for the program or subprogram as shown in the current Baseline Estimate for the program or subprogram; or
        • (ii) at least 50 percent over the procurement unit cost for the program or subprogram as shown in the original Baseline Estimate for the program or subprogram.
    • (4) The term “Baseline Estimate”, with respect to a unit cost report that is submitted under this chapter to the service acquisition executive designated by the Secretary concerned on a major defense acquisition program or designated major subprogram, means the cost estimate included in the baseline description for the program or subprogram under section 4214 of this title .
    • (5) The term “original Baseline Estimate” has the same meaning as provided in section 4214(d) of this title .
    • (6) The term “procurement program” means a program for which funds for procurement are authorized to be appropriated in a fiscal year.
  • (b) Reporting under this chapter shall not apply if a program has received a limited reporting waiver under section 4351(h) of this title .
  • (c) Any determination of a percentage increase under this chapter shall be stated in terms of constant base year dollars (as described in section 4202 of this title ).