33 U.S.C. § 16

Title 33 Chapter 15 Current through PL 119-73 Last updated: March 29, 2026 View on OLRC →
Sections in this chapter

§ 701b–16. Management of flood risk reduction projects

  • (a) If 2 or more flood control projects are located within the same geographic area, the Secretary shall, at the request of the non-Federal interests for the affected projects, consider those projects as a single program for budgetary or project management purposes, if the Secretary determines that doing so would not be incompatible with the authorized project purposes.
  • (b)
    • (1) If any work on a project to which subsection (a) applies is required solely because of impacts to that project from a navigation project, the cost of carrying out that work shall be shared in accordance with the cost-sharing requirements for the navigation project.
    • (2) Work described in paragraph (1) may be carried out using amounts made available under subsection (a).